Marlin Manor Pipe Improvements

This project consists of the replacement of approximately 8,000 feet of water main in the Marlin Manor subdivision, approximately 1,500 feet of water main along Revilla Lane, and approximately 4,000 feet of water main along Pluckebaum Road.  Additional improvements include the installation of new fire hydrants and service lines.

Status Construction
Design Start August 2015
Design Completion August 2021
Construction Start December 2021
Construction Completion March2023
Spent Budget  $2,295,320
Total Budget  $3,527,047
Percent Construction Complete  95%

                                                  Statistics as of February 2023