Groundwater pH Adjustment Project

This project at the Dyal Water Treatment Plant (WTP) adds a new calcium hydroxide chemical injection point to the groundwater treatment train downstream of the filters to control finished water pH.  This prevents scale buildup within the filters and allows the pH of treated water to be raised to a level that minimizes corrosion and nitrification in the distribution system.

Status Completed
Start March 2019
Completion June 2021
Spent Budget $255,878
Total Budget $255,878
Percent Complete 100%

Project Completed